Local Public Agency (LPA) Projects Archive Details

County Baldwin
ALDOT Project Number: 100061656
F/A Project Number: QTDG-0214(253)
Project Status: Authorized
Authorized/Letting Date: 08/06/2014
Route:
Program ID: QTDG
Federal Appropriation: QTDG
Project Scope: Construction
Work Description: RESURFACING, COMPLETE STREETS, SHARED USE PATHS, PEDESTRIAN BRIDGE AND SIDEWALKS IN THE CITY OF FOLEY
Estimated Completion Date: 10/31/2014
Federal Funding: $4,728,507.00
State Funding: $0.00
Local Funding: $0.00
Total Funding: $4,728,507.00
County Baldwin
ALDOT Project Number: 100061692
F/A Project Number: QTDG-0214(255)
Project Status: Authorized
Authorized/Letting Date: 07/11/2014
Route:
Program ID: QTDG
Federal Appropriation: QTDG
Project Scope: Construction
Work Description: CONSTRUCTION OF 13 MILES OF SHARED USE PATHS AND SIDEWALKS IN THE CITY OF FOLEY
Estimated Completion Date: 10/31/2014
Federal Funding: $0.00
State Funding: $0.00
Local Funding: $0.00
Total Funding: $0.00
County Baldwin
ALDOT Project Number: 100063680
F/A Project Number:
Project Status: Authorized
Authorized/Letting Date: 08/04/2015
Route:
Program ID: 99004
Federal Appropriation:
Project Scope: Maintenance Construction
Work Description: CONSTRUCTION OF CONNECTOR ROAD IN FOLEY FROM SR-59 TO PINE ST
Estimated Completion Date: 12/31/2015
Federal Funding: $0.00
State Funding: $250,000.00
Local Funding: $0.00
Total Funding: $250,000.00
County $385,000.00
ALDOT Project Number: 100065308
F/A Project Number: STPOA-0104(509)
Project Status: Planned
Authorized/Letting Date:
Route: SR-104
Program ID: USES
Federal Appropriation: Z231
Project Scope: Construction
Work Description: INTERSECTION IMPROVEMENTS - TURNING LANE ON SR-104 AT HIGBEE ROAD
Estimated Completion Date: 10/31/2016
Federal Funding: $308,000.00
State Funding: $0.00
Local Funding: $77,000.00
Total Funding: $385,000.00
County Baldwin
ALDOT Project Number: 100065665
F/A Project Number: STPOA-0216()
Project Status: Planned
Authorized/Letting Date:
Route: CR-30
Program ID: USES
Federal Appropriation: Z231
Project Scope: Construction
Work Description: CONSTRUCT SIDEWALK ON GAYFER ROAD EXTENSION (CR-30) FROM BISHOP ROAD TO MEADOWBROOK DRIVE
Estimated Completion Date: 05/31/2017
Federal Funding: $88,880.00
State Funding: $0.00
Local Funding: $22,220.00
Total Funding: $111,100.00
County Barbour
ALDOT Project Number: 100063738
F/A Project Number:
Project Status: Authorized
Authorized/Letting Date: 06/15/2015
Route:
Program ID: STATO
Federal Appropriation:
Project Scope: Construction
Work Description: IMPROVEMENTS TO VARIOUS STREETS IN THE CITY OF EUFAULA
Estimated Completion Date: 09/30/2015
Federal Funding: $0.00
State Funding: $350,000.00
Local Funding: $0.00
Total Funding: $350,000.00
County Barbour
ALDOT Project Number: 100064596
F/A Project Number:
Project Status: Authorized
Authorized/Letting Date: 08/17/2015
Route:
Program ID: IARA
Federal Appropriation:
Project Scope: Construction
Work Description: INDUSTRIAL ACCESS ROAD IMPROVEMENTS ON ARCH DRIVE AND DALE ROAD TO BENEFIT CARBO CERAMICS IN THE CITY OF EUFAULA
Estimated Completion Date: 03/31/2016
Federal Funding: $0.00
State Funding: 709,700.00
Local Funding: $0.00
Total Funding: 709,700.00
County Chilton
ALDOT Project Number: 100063596
F/A Project Number:
Project Status: Authorized
Authorized/Letting Date: 11/18/2015
Route: SR-22
Program ID: IARA
Federal Appropriation:
Project Scope: Construction
Work Description: WIDENING AND RESURFACING OF SR-22 FROM APPROXIMATELY 910' SOUTH OF CR-310 TO 760' NORTH OF CR-310, ALONG WITH INTERSECTION IMPROVEMENTS AT SR-22 AND CR-310, AND THE RECONSTRUCTION OF CR-310 FROM SR-22 FOR 1000' TO BENEFIT WEST FRASER MILL.
Estimated Completion Date: 06/30/2016
Federal Funding: $0.00
State Funding: $801,000.00
Local Funding: $0.00
Total Funding: $801,000.00
County Clarke
ALDOT Project Number: 100065148
F/A Project Number:
Project Status: Authorized
Authorized/Letting Date: 12/08/2015
Route: SR-13
Program ID: IARA
Federal Appropriation:
Project Scope: Construction
Work Description: RIGHT TURN LANE AND ACCELERATION LANE ON SR-13(US-43) AT ISPICEFOODS FACILITY
Estimated Completion Date: 01/31/2016
Federal Funding: $0.00
State Funding: $706,300.00
Local Funding: $0.00
Total Funding: $706,300.00
County Coffee
ALDOT Project Number: 100062437
F/A Project Number:
Project Status: Authorized
Authorized/Letting Date: 07/25/2014
Route:
Program ID: IARA
Federal Appropriation:
Project Scope: Construction
Work Description: IA ROAD IMP ON INDUSTRIAL BLVD IN ELBA INDUSTRIAL PARK TO BENEFIT SOUTHERN TRAILER WORKS, DORSEY TRAILER, POPE TENT, HICKMAN MOVING CO, AND ELBA INDUSTRIAL PARK; CITY OF ELBA
Estimated Completion Date: 10/31/2014
Federal Funding: $0.00
State Funding: $513,100.00
Local Funding: $0.00
Total Funding: $513,100.00
County Covington
ALDOT Project Number: 100063311
F/A Project Number:
Project Status: Authorized
Authorized/Letting Date: 12/19/2014
Route:
Program ID: IARA
Federal Appropriation:
Project Scope: Construction
Work Description: IAR IMPROVEMENTS ON DOUGLAS STREET TO BENEFIT GEORGIA AEROSPACE AND DEFENSE MANUFACTURING, LLC. CITY OF OPP.
Estimated Completion Date: 06/30/2015
Federal Funding: $0.00
State Funding: $748,800.00
Local Funding: $0.00
Total Funding: $748,800.00
County Covington
ALDOT Project Number: 100065710
F/A Project Number:
Project Status: Authorized
Authorized/Letting Date: 06/10/2016
Route: CR-NA
Program ID: STATO
Federal Appropriation:
Project Scope: Construction
Work Description: RESURFACING VARIOUS STREETS IN THE CITY OF ANDALUSIA
Estimated Completion Date: 02/28/2017
Federal Funding: $0.00
State Funding: $500,000.00
Local Funding: $0.00
Total Funding: $500,000.00
County Cullman
ALDOT Project Number: 100063681
F/A Project Number:
Project Status: Authorized
Authorized/Letting Date: 06/08/2015
Route:
Program ID: STATO
Federal Appropriation:
Project Scope: Construction
Work Description: RESURFACE SCHOOL HOUSE ROAD FROM SR-69 TO SUMMIT ROAD
Estimated Completion Date: 09/30/2015
Federal Funding: $0.00
State Funding: $150,000.00
Local Funding: $0.00
Total Funding: $150,000.00
County Etowah
ALDOT Project Number: 100061469
F/A Project Number: STPOA-UR13(606)
Project Status: Authorized
Authorized/Letting Date: 07/31/2014
Route:
Program ID: GDSTE
Federal Appropriation: L20E
Project Scope: Construction
Work Description: RESURFACING OF PADENREICH AVENUE, FORREST AVENUE AND 9TH STREET IN THE CITY OF GADSDEN
Estimated Completion Date: 04/30/2015
Federal Funding: $762,132.92
State Funding: $0.00
Local Funding: $0.00
Total Funding: $952,666.15
County Franklin
ALDOT Project Number: 100063561
F/A Project Number:
Project Status: Authorized
Authorized/Letting Date: 04/21/2015
Route:
Program ID: STATE
Federal Appropriation:
Project Scope: Construction
Work Description: IMPROVEMENTS TO LAWRENCE STREET IN THE CITY OF RUSSELLVILLE FROM SR-13 (US-43) TO THE INTERSECTION OF THE INDUSTRIAL ACCESS PROJECT FOR INNOVATIVE HEARTH PRODUCTS
Estimated Completion Date: 07/31/2015
Federal Funding: $0.00
State Funding: $200,000.00
Local Funding: $0.00
Total Funding: $200,000.00
County Geneva
ALDOT Project Number: 100063387
F/A Project Number:
Project Status: Authorized
Authorized/Letting Date: 02/03/2015
Route:
Program ID: STATE
Federal Appropriation:
Project Scope: Construction
Work Description: RESURFACING VARIOUS ROADS IN THE CITY OF SAMSON, GENEVA COUNTY
Estimated Completion Date: 05/31/2015
Federal Funding: $0.00
State Funding: $150,000.00
Local Funding: $0.00
Total Funding: $150,000.00
County Geneva
ALDOT Project Number: 100063593
F/A Project Number:
Project Status: Authorized
Authorized/Letting Date: 04/13/2015
Route:
Program ID: IARA
Federal Appropriation:
Project Scope: Construction
Work Description: IAR IMPROVEMENTS ON SR-52 AND SOUTH JORDAN ST. TO BENEFIT PROJECT MANDM-BROOKS PEANUT COMPANY IN THE CITY OF SAMSON
Estimated Completion Date: 08/31/2015
Federal Funding: $0.00
State Funding: $343,500.00
Local Funding: $0.00
Total Funding: $343,500.00
County Hale
ALDOT Project Number: 100058295
F/A Project Number:
Project Status: Planned
Authorized/Letting Date:
Route: CR-NA
Program ID: STATO
Federal Appropriation:
Project Scope: Construction
Work Description: MOUNDVILLE PARKWAY FROM CR-21 (MARKET STREET) TO MOUND PARKWAY IN THE CITY OF MOUNDVILLE
Estimated Completion Date: 11/30/2016
Federal Funding: $0.00
State Funding: $625,000.00
Local Funding: $0.00
Total Funding: $625,000.00
County Jefferson
ALDOT Project Number: 100039856
F/A Project Number: CMAQ-3700(213)
Project Status: Authorized
Authorized/Letting Date: 12/13/2012
Route:
Program ID: CMAME
Federal Appropriation: M40E
Project Scope: Construction
Work Description: RAILROAD RESERVATION PHASE 1 ENGINEERING: 1ST AVENUE SOUTH FROM 14TH. STREET TO 18TH STREET
Estimated Completion Date: 02/28/2013
Federal Funding: $377,600.00
State Funding: $0.00
Local Funding: $0.00
Total Funding: $472,000.00
County Jefferson
ALDOT Project Number: 100056474
F/A Project Number: STPBH-CN13(905)
Project Status: Authorized
Authorized/Letting Date: 02/14/2013
Route: I-59
Program ID: STBHR
Federal Appropriation: L23R
Project Scope: Construction
Work Description: GATEWAY IMPROVEMENTS ON I-20/59 FROM 31ST STREET NORTH TO MESSER AIRPORT HIGHWAY.
Estimated Completion Date: 04/30/2013
Federal Funding: $407,933.44
State Funding: $6,548.93
Local Funding: $0.00
Total Funding: $510,865.41
County Jefferson
ALDOT Project Number: 100063446
F/A Project Number:
Project Status: Authorized
Authorized/Letting Date: 03/04/2015
Route:
Program ID: STATO
Federal Appropriation:
Project Scope: Construction
Work Description: IMPROVEMENTS ON VARIOUS CITY STREETS IN THE CITY OF BIRMINGHAM
Estimated Completion Date: 01/31/2016
Federal Funding: $0.00
State Funding: $650,000.00
Local Funding: $0.00
Total Funding: $650,000.00
County Limestone
ALDOT Project Number: 100065390
F/A Project Number: ER-9010(904)
Project Status: Authorized
Authorized/Letting Date: 12/24/2015
Route: CR-25
Program ID: ERLF
Federal Appropriation: M9VE
Project Scope: Construction
Work Description: EMERGENCY REPAIRS TO REPLACE FAILED ARCH PIPE WITH DOUBLE BARREL 10X8 CULVERT ON SHAW ROAD (CR-25) LOCATED APPROXIMATELY 4,000' NORTH OF NUCLEAR PLANT ROAD. FHWA DISASTER #AL 16-1 (REPORT #LIMESTONE-1).
Estimated Completion Date: 10/31/2016
Federal Funding: $244,205.00
State Funding: $0.00
Local Funding: $0.00
Total Funding: $244,205.00
County Mobile
ALDOT Project Number: 100054353
F/A Project Number: STPTE-TE09(984)
Project Status: Authorized
Authorized/Letting Date: 07/01/2010
Route:
Program ID: STTEL
Federal Appropriation: L220
Project Scope: Construction
Work Description: LANDSCAPING, PEDESTRIAN LIGHTING AND SIGNS ALONG SR-13 (US- 43) IN THE CITY OF SATSUMA.
Estimated Completion Date: 10/31/2011
Federal Funding: $323,637.60
State Funding: $0.00
Local Funding: $0.00
Total Funding: $404,547.00
County Mobile
ALDOT Project Number: 100063100
F/A Project Number: HSIP-0042(530)
Project Status: Authorized
Authorized/Letting Date: 12/10/2015
Route: SR-42
Program ID: HSME
Federal Appropriation: MS3E
Project Scope: Construction
Work Description: CONSTRUCT OFFSET LEFT TURN LANES AND A WEST BOUND RIGHT TURN ON SR-42 (US-98) AT THE INTERSECTION OF MCCRARY ROAD (CR-27)
Estimated Completion Date: 02/29/2016
Federal Funding: $675,000.00
State Funding: $75,000.00
Local Funding: $0.00
Total Funding: $750,000.00
County Mobile
ALDOT Project Number: 100063468
F/A Project Number:
Project Status: Authorized
Authorized/Letting Date: 10/16/2015
Route:
Program ID: STATO
Federal Appropriation:
Project Scope: Construction
Work Description: RESURFACING BIENVILLE BOULEVARD FROM THREE WAY STOP TO BILLY GOAT HOLE (FERRY DOCK) IN THE TOWN OF DAUPHIN ISLAND
Estimated Completion Date: 12/31/2015
Federal Funding: $0.00
State Funding: $225,000.00
Local Funding: $0.00
Total Funding: $225,000.00
County
ALDOT Project Number:
F/A Project Number:
Project Status:
Authorized/Letting Date: 06/01/2016
Route: CR-31
Program ID: STATO
Federal Appropriation:
Project Scope: Construction
Work Description: ADDITIONAL LANES ON SCHILLINGER ROAD SOUTH (CR-31) FROM THREE NOTCH ROAD (CR-32) TO APPROXIMATELY 0.2 MILES SOUTH OF HALLS MILL CREEK.
Estimated Completion Date: 03/31/2018
Federal Funding: $0.00
State Funding: $10,000,000.00
Local Funding: $0.00
Total Funding: $10,000,000.00
County Pike
ALDOT Project Number: 100064598
F/A Project Number:
Project Status: Authorized
Authorized/Letting Date: 08/17/2015
Route:
Program ID: IARA
Federal Appropriation:
Project Scope: Construction
Work Description: EXTEND MAGNOLIA BOULEVARD. IN THE EXISTING NORTH INDUSTRIAL PARK TO THE PROPOSED FOOD PROCESSING FACILITY TO BENEFIT MAGNOLIA VEGETABLE PROCESSORS LLC., IN THE CITY OF BRUNDIDGE
Estimated Completion Date: 01/31/2016
Federal Funding: $0.00
State Funding: $472,300.00
Local Funding: $0.00
Total Funding: $472,300.00
County St. Clair
ALDOT Project Number: 100063619
F/A Project Number:
Project Status: Authorized
Authorized/Letting Date: 07/21/2015
Route:
Program ID: STATO
Federal Appropriation:
Project Scope: Construction
Work Description: WIDEN AND RESURFACE VARIOUS STREETS IN THE TOWN OF RAGLAND
Estimated Completion Date: 09/30/2015
Federal Funding: $0.00
State Funding: $30,000.00
Local Funding: $0.00
Total Funding: $30,000.00
County Sumter
ALDOT Project Number: 100064576
F/A Project Number:
Project Status: Authorized
Authorized/Letting Date: 08/04/2015
Route:
Program ID: IARA
Federal Appropriation:
Project Scope: Construction
Work Description: ACCESS ROAD IMPROVEMENTS ON JACKSON STREET AND KENTUCKY AVENUE TO BENEFIT SOUTHWEST PAPER SALES (OPERATING AS K AND Z, LLC) IN THE CITY OF YORK
Estimated Completion Date: 11/30/2015
Federal Funding: $0.00
State Funding: $265,200.00
Local Funding: $0.00
Total Funding: $265,200.00

Click on any project to view details on that project.