ALDOT Project Number: | 100061656 |
F/A Project Number: | QTDG-0214(253) |
Project Status: | Authorized |
Authorized/Letting Date: | 08/06/2014 |
Route: | |
Program ID: | QTDG |
Federal Appropriation: | QTDG |
Project Scope: | Construction |
Work Description: | Resurfacing, complete streets, shared use paths, pedestrian bridge and sidewalks in the City of Foley |
Estimated Completion Date: | 10/31/2014 |
Federal Funding: | $4,728,507.00 |
State Funding: | $0.00 |
Local Funding: | $0.00 |
Total Funding: | $4,728,507.00 |
County | Baldwin |
---|---|
ALDOT Project Number: | 100061692 |
F/A Project Number: | QTDG-0214(255) |
Project Status: | Authorized |
Authorized/Letting Date: | 07/11/2014 |
Route: | |
Program ID: | QTDG |
Federal Appropriation: | QTDG |
Project Scope: | Construction |
Work Description: | Construction of 13 miles of shared use paths and sidewalks in the City of Foley |
Estimated Completion Date: | 10/31/2014 |
Federal Funding: | $0.00 |
State Funding: | $0.00 |
Local Funding: | $0.00 |
Total Funding: | $0.00 |
County | Baldwin |
---|---|
ALDOT Project Number: | 100063680 |
F/A Project Number: | |
Project Status: | Authorized |
Authorized/Letting Date: | 08/04/2015 |
Route: | |
Program ID: | 99004 |
Federal Appropriation: | |
Project Scope: | Maintenance Construction |
Work Description: | Construction of connector road in Foley form SR-59 to Pine St |
Estimated Completion Date: | 12/31/2015 |
Federal Funding: | $0.00 |
State Funding: | $250,000.00 |
Local Funding: | $0.00 |
Total Funding: | $250,000.00 |
County | $385,000.00 |
---|---|
ALDOT Project Number: | 100065308 |
F/A Project Number: | STPOA-0104(509) |
Project Status: | Planned |
Authorized/Letting Date: | |
Route: | SR-104 |
Program ID: | USES |
Federal Appropriation: | Z231 |
Project Scope: | Construction |
Work Description: | Intersection Improvements - Turning lane on SR-104 at Higbee Road |
Estimated Completion Date: | 10/31/2016 |
Federal Funding: | $308,000.00 |
State Funding: | $0.00 |
Local Funding: | $77,000.00 |
Total Funding: | $385,000.00 |
County | Baldwin |
---|---|
ALDOT Project Number: | 100065665 |
F/A Project Number: | STPOA-0216() |
Project Status: | Planned |
Authorized/Letting Date: | |
Route: | CR-30 |
Program ID: | USES |
Federal Appropriation: | Z231 |
Project Scope: | Construction |
Work Description: | Construct sidewalk on Gayfer Road Extension (CR-30) from Bishop Road to Meadowbrook Drive |
Estimated Completion Date: | 05/31/2017 |
Federal Funding: | $88,880.00 |
State Funding: | $0.00 |
Local Funding: | $22,220.00 |
Total Funding: | $111,100.00 |
County | Barbour |
---|---|
ALDOT Project Number: | 100063738 |
F/A Project Number: | |
Project Status: | Authorized |
Authorized/Letting Date: | 06/15/2015 |
Route: | |
Program ID: | STATO |
Federal Appropriation: | |
Project Scope: | Construction |
Work Description: | Improvements to various streets in the City of Eufaula |
Estimated Completion Date: | 09/30/2015 |
Federal Funding: | $0.00 |
State Funding: | $350,000.00 |
Local Funding: | $0.00 |
Total Funding: | $350,000.00 |
County | Barbour |
---|---|
ALDOT Project Number: | 100064596 |
F/A Project Number: | |
Project Status: | Authorized |
Authorized/Letting Date: | 08/17/2015 |
Route: | |
Program ID: | IARA |
Federal Appropriation: | |
Project Scope: | Construction |
Work Description: | Industrial access road improvements on Arch Drive and Dale Road to benefit Carbo Ceramics in the City of Eufaula |
Estimated Completion Date: | 03/31/2016 |
Federal Funding: | $0.00 |
State Funding: | 709,700.00 |
Local Funding: | $0.00 |
Total Funding: | 709,700.00 |
County | Chilton |
---|---|
ALDOT Project Number: | 100063596 |
F/A Project Number: | |
Project Status: | Authorized |
Authorized/Letting Date: | 11/18/2015 |
Route: | SR-22 |
Program ID: | IARA |
Federal Appropriation: | |
Project Scope: | Construction |
Work Description: | Widening and resurfacing of SR-22 from approximately 910' South of CR-310 to 760' North of CR-310, along with Intersection Improvements at SR-22 and CR-310, and the reconstruction of CR-310 from SR-22 for 1000' to benefit West Fraser Mill |
Estimated Completion Date: | 06/30/2016 |
Federal Funding: | $0.00 |
State Funding: | $801,000.00 |
Local Funding: | $0.00 |
Total Funding: | $801,000.00 |
County | Clarke |
---|---|
ALDOT Project Number: | 100065148 |
F/A Project Number: | |
Project Status: | Authorized |
Authorized/Letting Date: | 12/08/2015 |
Route: | SR-13 |
Program ID: | IARA |
Federal Appropriation: | |
Project Scope: | Construction |
Work Description: | Right turn lane and acceleration lane on SR-13(US-43) at iSpice foods facility |
Estimated Completion Date: | 01/31/2016 |
Federal Funding: | $0.00 |
State Funding: | $706,300.00 |
Local Funding: | $0.00 |
Total Funding: | $706,300.00 |
County | Coffee |
---|---|
ALDOT Project Number: | 100062437 |
F/A Project Number: | |
Project Status: | Authorized |
Authorized/Letting Date: | 07/25/2014 |
Route: | |
Program ID: | IARA |
Federal Appropriation: | |
Project Scope: | Construction |
Work Description: | IA Road IMP on Industrial Blvd in Elba Industrial Park to benefit Southern Trailer Works, Dorsey Trailer, Pope Tent, Hickman Moving Co. and Elba Industrial Park, City of Elba |
Estimated Completion Date: | 10/31/2014 |
Federal Funding: | $0.00 |
State Funding: | $513,100.00 |
Local Funding: | $0.00 |
Total Funding: | $513,100.00 |
County | Covington |
---|---|
ALDOT Project Number: | 100063311 |
F/A Project Number: | |
Project Status: | Authorized |
Authorized/Letting Date: | 12/19/2014 |
Route: | |
Program ID: | IARA |
Federal Appropriation: | |
Project Scope: | Construction |
Work Description: | IAR Improvements on Douglas Street to benefit Georgia Aerospace and Defense Manufacturing, LLC. City of Opp |
Estimated Completion Date: | 06/30/2015 |
Federal Funding: | $0.00 |
State Funding: | $748,800.00 |
Local Funding: | $0.00 |
Total Funding: | $748,800.00 |
County | Covington |
---|---|
ALDOT Project Number: | 100065710 |
F/A Project Number: | |
Project Status: | Authorized |
Authorized/Letting Date: | 06/10/2016 |
Route: | CR-NA |
Program ID: | STATO |
Federal Appropriation: | |
Project Scope: | Construction |
Work Description: | Resurfacing various streets in the City of Andalusia |
Estimated Completion Date: | 02/28/2017 |
Federal Funding: | $0.00 |
State Funding: | $500,000.00 |
Local Funding: | $0.00 |
Total Funding: | $500,000.00 |
County | Cullman |
---|---|
ALDOT Project Number: | 100063681 |
F/A Project Number: | |
Project Status: | Authorized |
Authorized/Letting Date: | 06/08/2015 |
Route: | |
Program ID: | STATO |
Federal Appropriation: | |
Project Scope: | Construction |
Work Description: | Resurface School House Road from SR-69 to Summit Road |
Estimated Completion Date: | 09/30/2015 |
Federal Funding: | $0.00 |
State Funding: | $150,000.00 |
Local Funding: | $0.00 |
Total Funding: | $150,000.00 |
County | Etowah |
---|---|
ALDOT Project Number: | 100061469 |
F/A Project Number: | STPOA-UR13(606) |
Project Status: | Authorized |
Authorized/Letting Date: | 07/31/2014 |
Route: | |
Program ID: | GDSTE |
Federal Appropriation: | L20E |
Project Scope: | Construction |
Work Description: | Resurfacing of Padenreich Avenue, Forrest Avenue and 9th Street in the City of Gadsden |
Estimated Completion Date: | 04/30/2015 |
Federal Funding: | $762,132.92 |
State Funding: | $0.00 |
Local Funding: | $0.00 |
Total Funding: | $952,666.15 |
County | Franklin |
---|---|
ALDOT Project Number: | 100063561 |
F/A Project Number: | |
Project Status: | Authorized |
Authorized/Letting Date: | 04/21/2015 |
Route: | |
Program ID: | STATE |
Federal Appropriation: | |
Project Scope: | Construction |
Work Description: | Improvements to Lawrence Street in the City of Russellville from SR-13 (US-43) to the Intersection of the Industrial Access project for innovative hearth products |
Estimated Completion Date: | 07/31/2015 |
Federal Funding: | $0.00 |
State Funding: | $200,000.00 |
Local Funding: | $0.00 |
Total Funding: | $200,000.00 |
County | Geneva |
---|---|
ALDOT Project Number: | 100063387 |
F/A Project Number: | |
Project Status: | Authorized |
Authorized/Letting Date: | 02/03/2015 |
Route: | |
Program ID: | STATE |
Federal Appropriation: | |
Project Scope: | Construction |
Work Description: | Resurfacing various roads in the City of Samson, Geneva County |
Estimated Completion Date: | 05/31/2015 |
Federal Funding: | $0.00 |
State Funding: | $150,000.00 |
Local Funding: | $0.00 |
Total Funding: | $150,000.00 |
County | Geneva |
---|---|
ALDOT Project Number: | 100063593 |
F/A Project Number: | |
Project Status: | Authorized |
Authorized/Letting Date: | 04/13/2015 |
Route: | |
Program ID: | IARA |
Federal Appropriation: | |
Project Scope: | Construction |
Work Description: | IAR Improvements on SR-52 and South Jordan St. to benefit project MANDM-BROOKS Peanut Companyin the City of Samson |
Estimated Completion Date: | 08/31/2015 |
Federal Funding: | $0.00 |
State Funding: | $343,500.00 |
Local Funding: | $0.00 |
Total Funding: | $343,500.00 |
County | Hale |
---|---|
ALDOT Project Number: | 100058295 |
F/A Project Number: | |
Project Status: | Planned |
Authorized/Letting Date: | |
Route: | CR-NA |
Program ID: | STATO |
Federal Appropriation: | |
Project Scope: | Construction |
Work Description: | Moundville Parkway from CR-21 (Market Street) to Mound Parkway in the City of Moundville |
Estimated Completion Date: | 11/30/2016 |
Federal Funding: | $0.00 |
State Funding: | $625,000.00 |
Local Funding: | $0.00 |
Total Funding: | $625,000.00 |
County | Jefferson |
---|---|
ALDOT Project Number: | 100039856 |
F/A Project Number: | CMAQ-3700(213) |
Project Status: | Authorized |
Authorized/Letting Date: | 12/13/2012 |
Route: | |
Program ID: | CMAME |
Federal Appropriation: | M40E |
Project Scope: | Construction |
Work Description: | Railroad Reservation Phase 1 Engineering: 1st Avenue South form 14th Street ti 18th Street |
Estimated Completion Date: | 02/28/2013 |
Federal Funding: | $377,600.00 |
State Funding: | $0.00 |
Local Funding: | $0.00 |
Total Funding: | $472,000.00 |
County | Jefferson |
---|---|
ALDOT Project Number: | 100056474 |
F/A Project Number: | STPBH-CN13(905) |
Project Status: | Authorized |
Authorized/Letting Date: | 02/14/2013 |
Route: | I-59 |
Program ID: | STBHR |
Federal Appropriation: | L23R |
Project Scope: | Construction |
Work Description: | Gateway Improvements on I-20/59 from 31st Street North to Messer Airport Highway |
Estimated Completion Date: | 04/30/2013 |
Federal Funding: | $407,933.44 |
State Funding: | $6,548.93 |
Local Funding: | $0.00 |
Total Funding: | $510,865.41 |
County | Jefferson |
---|---|
ALDOT Project Number: | 100063446 |
F/A Project Number: | |
Project Status: | Authorized |
Authorized/Letting Date: | 03/04/2015 |
Route: | |
Program ID: | STATO |
Federal Appropriation: | |
Project Scope: | Construction |
Work Description: | Improvements on various City streets in the City of Birmingham |
Estimated Completion Date: | 01/31/2016 |
Federal Funding: | $0.00 |
State Funding: | $650,000.00 |
Local Funding: | $0.00 |
Total Funding: | $650,000.00 |
County | Limestone |
---|---|
ALDOT Project Number: | 100065390 |
F/A Project Number: | ER-9010(904) |
Project Status: | Authorized |
Authorized/Letting Date: | 12/24/2015 |
Route: | CR-25 |
Program ID: | ERLF |
Federal Appropriation: | M9VE |
Project Scope: | Construction |
Work Description: | Emergency repairs to replace failed arch pipe with double barrel 10X8 Culvert on Shaw Road (CR-25) located approximately 4,000' North of Nuclear Plant Road. FHWA Disaster #AL 16-1 (Report #Limestone-1). |
Estimated Completion Date: | 10/31/2016 |
Federal Funding: | $244,205.00 |
State Funding: | $0.00 |
Local Funding: | $0.00 |
Total Funding: | $244,205.00 |
County | Mobile |
---|---|
ALDOT Project Number: | 100054353 |
F/A Project Number: | STPTE-TE09(984) |
Project Status: | Authorized |
Authorized/Letting Date: | 07/01/2010 |
Route: | |
Program ID: | STTEL |
Federal Appropriation: | L220 |
Project Scope: | Construction |
Work Description: | Landscaping, pedestrian lighting and signs along SR-13 (US- 43) in the City of Satsuma |
Estimated Completion Date: | 10/31/2011 |
Federal Funding: | $323,637.60 |
State Funding: | $0.00 |
Local Funding: | $0.00 |
Total Funding: | $404,547.00 |
County | Mobile |
---|---|
ALDOT Project Number: | 100063100 |
F/A Project Number: | HSIP-0042(530) |
Project Status: | Authorized |
Authorized/Letting Date: | 12/10/2015 |
Route: | SR-42 |
Program ID: | HSME |
Federal Appropriation: | MS3E |
Project Scope: | Construction |
Work Description: | Construct offset left turn lanes and a West bound right turn on SR-42 (US-98) at the intersection of McCarary Road (CR-27) |
Estimated Completion Date: | 02/29/2016 |
Federal Funding: | $675,000.00 |
State Funding: | $75,000.00 |
Local Funding: | $0.00 |
Total Funding: | $750,000.00 |
County | Mobile |
---|---|
ALDOT Project Number: | 100063468 |
F/A Project Number: | |
Project Status: | Authorized |
Authorized/Letting Date: | 10/16/2015 |
Route: | |
Program ID: | STATO |
Federal Appropriation: | |
Project Scope: | Construction |
Work Description: | Resurfacing Bienville Boulevard from Three Way stop to Billy Goat Hole (Ferry Dock) in the Town of Dauphin Island |
Estimated Completion Date: | 12/31/2015 |
Federal Funding: | $0.00 |
State Funding: | $225,000.00 |
Local Funding: | $0.00 |
Total Funding: | $225,000.00 |
County | |
---|---|
ALDOT Project Number: | |
F/A Project Number: | |
Project Status: | |
Authorized/Letting Date: | 06/01/2016 |
Route: | CR-31 |
Program ID: | STATO |
Federal Appropriation: | |
Project Scope: | Construction |
Work Description: | Additional lanes on Schillinger Road South (CR-31) from Three Notch Road (CR-32) to approximatley 0.2 miles South of Halls Mill Creek |
Estimated Completion Date: | 03/31/2018 |
Federal Funding: | $0.00 |
State Funding: | $10,000,000.00 |
Local Funding: | $0.00 |
Total Funding: | $10,000,000.00 |
County | Pike |
---|---|
ALDOT Project Number: | 100064598 |
F/A Project Number: | |
Project Status: | Authorized |
Authorized/Letting Date: | 08/17/2015 |
Route: | |
Program ID: | IARA |
Federal Appropriation: | |
Project Scope: | Construction |
Work Description: | Extend Magnolia Boulevard. In the existing North Industrial Park to the proposed food processing facility to benefit Magnolia Vegetable Processors LLC., in the City of Brundidge |
Estimated Completion Date: | 01/31/2016 |
Federal Funding: | $0.00 |
State Funding: | $472,300.00 |
Local Funding: | $0.00 |
Total Funding: | $472,300.00 |
County | St. Clair |
---|---|
ALDOT Project Number: | 100063619 |
F/A Project Number: | |
Project Status: | Authorized |
Authorized/Letting Date: | 07/21/2015 |
Route: | |
Program ID: | STATO |
Federal Appropriation: | |
Project Scope: | Construction |
Work Description: | Widen and resurface various streets in the Town of Ragland |
Estimated Completion Date: | 09/30/2015 |
Federal Funding: | $0.00 |
State Funding: | $30,000.00 |
Local Funding: | $0.00 |
Total Funding: | $30,000.00 |
County | Sumter |
---|---|
ALDOT Project Number: | 100064576 |
F/A Project Number: | |
Project Status: | Authorized |
Authorized/Letting Date: | 08/04/2015 |
Route: | |
Program ID: | IARA |
Federal Appropriation: | |
Project Scope: | Construction |
Work Description: | Access Road improvements on Jackson Street and Kentucky Avenue to benefit Southwest Paper Sales (Operating AS K AND Z, LLC) In the City of York |
Estimated Completion Date: | 11/30/2015 |
Federal Funding: | $0.00 |
State Funding: | $265,200.00 |
Local Funding: | $0.00 |
Total Funding: | $265,200.00 |