The Transportation Improvement Program (TIP) is a minimum four-year program of transportation projects and strategies formally implementing the MPO transportation plan.
| Regulation | Description |
|---|---|
| 23 CFR 450.334(a) | Report due December 31st |
| 23 CFR 450.334(b) | Report should include a project listing |
| 23 CFR 450.334(b) | Report must have the following column headers: Engineer Estimate, Fed. Obligated, Fed. Expenditure, Balance |
| 23 CFR 450.334(c) | Report should be posted to website |
| Report should be a standalone document and include a narrative |
| Regulation | Description |
|---|---|
| Par. XII(b)(1) State of Alabama Department of Transportation June 24, 2016; Procedure for Selection of Architect and/or Engineer Services |
MPO determines need for consultants: a) assessment of workload; b) resources (manpower) within MPO; c) need for outside expertise |
| Par. XII(b)(1)(i) State of Alabama Department of Transportation June 24, 2016; Procedure for Selection of Architect and/or Engineer Services |
MPO sends written request to ALDOT Region Engineer requesting a copy of ALDOT’s On-Call Consultant (A & E Services) List. Request must contain: a) Justification for use of a consultant; b) Detailed scope of work |
| Par. XII(b)(1)(ii) State of Alabama Department of Transportation June 24, 2016; Procedure for Selection of Architect and/or Engineer Services |
ALDOT will transit a list of currently active “on-call consultants to the city/county/MPO. Upon receiving the list of consultants, the city/County/MPO will select one of the consultants listed and then enter into negotiations with the selected firm. |
| Par. XII(b)(1)(iv) State of Alabama Department of Transportation June 24, 2016; Procedure for Selection of Architect and/or Engineer Services |
Region Engineer determines approval or additional information needed. Determination: a) If approved, Region Engineer transmits letter of approval to MPO; b) If additional information is needed, the approval letter will be provided after the additional information is provided. |
| Par. XII(b)(1)(v) State of Alabama Department of Transportation June 24, 2016; Procedure for Selection of Architect and/or Engineer Services |
MPO selects consultant, negotiates agreement, and sends agreement to Region Engineer for approval. |
| Date | Activity | Responsible Party |
| September 1st | Adopt Unified Planning Work Program | MPO |
| September 1st | Adopt Work Program | RPO |
| Mid-September | Federal Management Information System (FMIS) shuts down for Federal close-out | FHWA |
For questions pertaining to the MPO Program contact James F. Boyer, P.E. at 334.242.6728.